Close up view from above of the building site.
Monday, October 27, 2008
Readiness and Anticipation
The words "readiness" and "anticipation" characterize where we are today with the Missions Building Project. The demolition and site preparation is completed. The steel building package has been delivered. What you see here are the dig outs for the footing. We are still working on some scheduling with the concrete contractor, but we plan to pour these footings starting late this week or the early part of the following week. A part of this will be the proper placement of the bolts that attach the building to its foundation. So today, all lays waiting in anticipation and readiness.
![](https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEjdD6K0qUF1FdblKft24p34rBJBy49fwx0JFjdakxaIc47p-DUCg3qRKHwTv2LseVxbaUkH2_SE5hhNSpBIrqeasMEg2KEr5IcnT3B5eWS1oTerHbActgZxpVz4HIY-ZxkGJerFGI4X2uY/s320/readiness2_edited-1.JPG)
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment